What the two methods are
Both methods get a new pipe into the ground. They differ in how much of the ground has to be opened to do it.
Digging, or open trench, means excavating along the whole route, laying the new pipe in the trench, testing it, backfilling and reinstating the surface. You can see the ground you are working in, which is its main advantage.
Moling, short for trenchless installation, works from two pits, one at each end of the run. A pneumatic tool drives a hole through the soil between them and the new pipe is pulled into the hole behind it or follows it. Thames Water's leakage code of practice, dated July 2025, uses this very term. It says that where it helps with a customer's supply pipe it will, where possible, use "trenchless technology known as moling" to insert new pipe, and that if it cannot avoid digging on a footpath or driveway it restores the surface to make it safe to use.
Side by side
| Open trench | Moling (trenchless) | |
|---|---|---|
| Ground opened | The full route, typically a narrow trench along the length | A pit at each end, and any pit needed at a joint or change of direction |
| Lawn or planting | Lifted and put back along the route | Mostly left alone between the pits |
| Block paving or slabs | Lifted along the route and relaid | Often left in place, with the pits the only openings |
| Concrete, tarmac or resin | Cut, broken and patched along the route | Cut only at the pits, which still need reinstating |
| Control | High. The route is visible and obstacles can be seen | Less. The tool follows the ground and the engineer works from the surface |
| If something is in the way | It is exposed and dealt with, or the trench goes around it | The mole can stop or deflect. The fallback is a trench or a new pit |
| Best for | Short runs, soft ground, routes that must be seen, awkward bends | Longer runs under surfaces you want to keep |
| Typical time on site | Depends on length and surface | Depends on the ground. Often quicker where it works |

These are general observations from the way the methods work. Your ground and your route will decide, and we say in the quote which one we expect to use and why. The shorter comparison on the water supply pipe replacement page is the summary. This page goes further into when each is possible.
What can stop or divert a mole
The tool drives through soil. It does not cut through everything. These are the usual reasons moling does not go to plan, and why a survey earns its keep:
- Tree roots. A thick root can deflect a mole or stop it. A route near a mature tree may need a trench, or a different line. Tree roots and water supply pipes goes into this.
- Old pipes and drains. An existing drain or a disused pipe crossing the route can be struck or can deflect the tool.
- Buried rubble, old footings and made ground. Much of London's ground has been dug and backfilled many times, and a route under a Victorian garden can hold bricks, slabs and old foundations. Water leaks in Victorian and Edwardian London houses says more about older properties.
- Other services. Gas, electricity, telecoms and drains may cross the route. The Health and Safety Executive's guidance on avoiding danger from underground services (HSG47) splits safe excavation into planning, finding and identifying buried services, and digging safely. That applies to a mole as much as a spade.
- Depth and gradient. A long run needs a consistent depth, and a mole that drifts can end up too shallow or too deep.
- Very hard or very loose ground. Some ground is awkward for either reason, which is a judgement the engineer makes on site.
These are practitioner observations. They describe the kinds of thing that go wrong and are not a prediction for your garden.
A good quote says what happens if the mole does not get through. The usual answer is that a pit or a section of trench is opened at the point of the problem. Ask whether that fallback is included in the price or is an extra. In our quotes, we say which it is.
Which surface is above the pipe

The surface above the route often makes the choice for you.
| Surface | Trench means | Moling means | Tends to favour |
|---|---|---|---|
| Lawn or borders | Turf lifted and relaid, planting disturbed | Pits at each end, mostly undisturbed between | Either. Moling if the line is clear |
| Block paving | Blocks lifted, bedding relaid, all pieces put back | Two or three block-sized openings | Moling, if the route allows it |
| Natural stone or crazy paving | Careful lifting and relaying by a specialist | A small number of openings | Moling where possible |
| Concrete or tarmac drive | Cut, broken out and patched along the route | Cut at the pits only | Moling where possible, with a visible patch at each end |
| Patio or decking over the route | Lifted along the route | Pits either side if there is room | Depends on access |
| Inside a building or under floors | Opens the floor | Rarely suitable | Case by case. Often a separate survey first |
Thames Water's code says it cannot undertake specialist work such as relaying block or crazy paving, and that in those cases it makes the area safe and you may arrange a specialist to relay the surface yourself at your own cost. That is a statement about its own help, and it is a fair prompt to ask any firm quoting what it will and will not put back. We list that in the written quote.
Permissions, depth and notices
On your own land, the decision is yours. Three things can add a step:
- Water regulations. The Water Supply (Water Fittings) Regulations 1999, regulation 5, lists some work that needs prior notice to the water company. In the version we read it includes laying underground pipe shallower than 750mm or deeper than 1350mm. A new pipe, whichever way it goes in, has to end up at a suitable depth, so we confirm for your job when we quote. The notes on how deep a water supply pipe is in the UK cover depth in general.
- Public ground. If a trench or a mole has to cross a pavement or road, that is a matter for the street authority. Section 50 of the New Roads and Street Works Act 1991 lets it grant street works licences covering breaking up or opening the street and tunnelling or boring under it. We do not assume what your job needs. Water leak under the pavement or road says more.
- A shared pipe. If neighbours share the supply, the part serving only your property is yours and the shared section is a joint responsibility. Thames Water says it does not step into disputes between neighbours. Agree who is paying before you start.
Once the work is done, Thames Water recommends you ask for a certificate of water regulations compliance. Ask any firm whether it can issue one. We are not on the WaterSafe register and claim no accreditation, and Thames Water recommends WaterSafe approved plumbers for visible leaks and approved leak detection contractors for hidden or outside leaks, so check any listing yourself at watersafe.org.uk and choose accordingly.
Why the choice starts with a survey
You cannot choose between a trench and a mole without knowing where the pipe is, how deep it runs, what is above it and what else is beneath it. A survey answers most of that without opening the ground:
- We trace the route with a pipe locator and mark it on the surface.
- We record the surface along the route, the likely depth and obstacles you can see, such as trees, walls and manholes.
- We test sections to separate a leak on one stretch from a pipe failing along its length.
- The written report says where the pipe runs and what we found. A quote for the new pipe follows if replacement is what the evidence supports.
A mains and supply pipe trace is charged at a fixed £450, however long the job takes, and No VAT charged. Tracer gas and the written report are included in the price. Pricing has the table. A survey does not guarantee that a mole will get through. It reduces the chance of a surprise, and it means a decision to dig is based on evidence and not a guess.
We do not publish prices for the new pipe. The cost depends on length, depth, surface and what must be put back, and trench and mole can differ either way for the same property. After the survey you receive a written quote that lists the route, the method, the reason for it and what is not included.
What happens on the day
A typical order of work looks like this. Exact steps depend on the job, so treat it as a guide.
| Step | Open trench | Moling |
|---|---|---|
| 1 | Water is isolated and neighbours on a shared supply are told | Water is isolated and neighbours on a shared supply are told |
| 2 | The route is marked and the surface is lifted or cut | Entry and exit pits are opened at each end |
| 3 | A trench is dug to the planned depth | The mole is driven between the pits along the marked line |
| 4 | New pipe is laid and jointed | New pipe is pulled in or follows the mole, then jointed |
| 5 | The pipe is pressure tested and checked for leaks | The pipe is pressure tested and checked for leaks |
| 6 | The trench is backfilled and compacted | The pits are backfilled and compacted |
| 7 | The surface is put back as the quote says | The pits are reinstated as the quote says |
The water is usually off for part of the day. We say how long in the quote, and we aim to reconnect you before we leave. The old pipe is often left in the ground and capped or disconnected, and we state in the quote what happens to it. Moving the stop tap or the meter is a separate matter, and the stop tap and meter are Thames Water's equipment.
Choosing between them
- Choose a trench when the run is short, the ground is soft and easy to restore, or the route has to be seen to avoid something.
- Choose a mole when the run is long, the line is clear and the surface above is expensive or awkward to put back.
- Expect a mixture on some jobs: a mole for most of the run and a short trench where it crosses something.
- Do not let the method be chosen by whoever turns up with a particular machine. Ask why.
To start, report a leak or call 020 3961 5444. More guides are in the guides hub.
How this comparison was made
Every figure in a comparison is dated and names its source. How we price our own work, and where the other numbers come from, is set out in how we price and source.